Click on Picture to Enlarge
Back to Home Page Back to Construction Table of Contents
Building Construction Moving the Storage Shed

07/21/08
07/22/08
07/22/08

7/22/08 Construction trailer arrives

New barn location

07/29/08 - Hooking up electricity to trailer

8/18/08 - Bringing in barn moving materials

08/14/08 - Getting ready

08/21/08 - Putting a few holes in the storage building

08/20/08 - Clearing trees for a new parking lot next to football field

08/21/08 - Preparing the soil for the foundation of existing barn

08/21/08 - Clearing trees for new parking lot near cafeteria

08/21/08 - Setting up the foundation forms

08/21/08 - Clearing part of "loop" for a new roadway

08/21/08 - More holes put into the current storage shed

08/21/08 - Clearing the area around the current VoAg Center

8/21/08 - Cement is here!

08/26/08 - Work continues on back parking lot

08/22/08 - Footings in place
 
08/28/08 - Work continues on parking lots

08/26/08 - Side walls ready for cement
 
10/02/08 - First coat on parking lot

08/26/08 - Garage lifted off foundation
 
9/22/08 - The double-wide trailer arrives

08/26/08 - How the garage was raised
 
9/22/08 - 10/03/08 Foundation and building walls going up.

Need a house moved?

11/03/08 - Work continues on the foundation.

Getting ready to roll - 08/28/08
 
12/07/08 - Foundation work almost complete

Starting the move - 09/05/08
 
12/07/08 - Just a little underground pipe

Finishing the move at 11:58 p.m. - 09/05/08

12/10/08 - Crane arrives on site

11/03/08 - Work continues on creating a new building wall.
     
01/02/09 - Crane moved into position (If the picture is to large - click on picture)

12/07/08 - I-Beams are removed from building.
           
01/06/09 - Steel work has been going on for 3 days
 
 
01/09/09 - Work continues with steel
 

01/27/09 - Decking is being applied to beams